Description

Fix an issue with creating tasks directly into milestone columns

Summary:
These columns were conflating projectPHID (the defualt project to add to the task) with boardPHID (the board the column appears on).

Separate them to fix the beahvior.

Test Plan: Used "Add Task" from dropdown menu of a milestone column on a parent project's workboard.

Reviewers: chad

Reviewed By: chad

Differential Revision: https://secure.phabricator.com/D15242

Details

Provenance
epriestley <git@epriestley.com>Authored on Feb 11 2016, 6:51 PM
Parents
rPHAB705c8c956af5: Fix one straggler milestone URI
Branches
Unknown
Tags
Unknown

Event Timeline

epriestley <git@epriestley.com> committed rPHABad77b014f10e: Fix an issue with creating tasks directly into milestone columns (authored by epriestley <git@epriestley.com>).Feb 11 2016, 7:01 PM